Notice of intent to demolish building “reasonably calculated” to inform owners of pending action

by Andrea Vaage

Yang v. City of Wyoming
Federal 6th Circuit Court of Appeals, July 13, 2015

Ming Kuo Yang and Julie Yang owned a commercial property in Wyoming, Michigan. The Yangs previously rented the property to a series of restaurants; eventually, the property was listed for sale in late 2010. The lease on the last restaurant ended in February 2011. The property was never sold and was then neglected. The owners continued to pay property taxes. In October 2011, city officials posted an abandonment notice on the building. The notice was also mailed to the address of the abandoned building, but listed the former owner as the recipient, not the Yangs. In July 2012, the city sent a “Notice and Order to Repair or Demolish” by signature-required certified mailing to the building address. This notice also listed the former owner as the recipient. Two months later, the post office returned the mail to the city as unclaimed. The City did a title search of the building and identified the Yangs as the correct owner. The City then sent both previous notices to the Yangs’ correct address by certified mail in September 2012.

The City did not receive a response from the Yangs. It then scheduled a hearing about demolishing the property for November 1, 2012. The City sent the Yangs a hearing notice by regular mail and also sent a notice to the Yangs’ realtor. Soon thereafter, the post office returned the original certified mailing to the Yangs as unclaimed. This information was not present. The Yangs did not appear to the hearing on November 1 where the board decided to demolish the property. The property was demolished in January 2013, and a $22,500 bill was sent to the Yangs’ address for the work.

The Yangs then discovered their building was demolished and claimed the city violated their procedural due process rights by demolishing the property without adequate notice. The standard of review is whether the City’s efforts were “reasonably calculated” to inform the Yangs of the action taken on their property. The City of Wyoming attempted to contact the Yangs through posted notices, mailed notices to the Yangs, mailed notice to the realtor, and the post-hearing notice. Michigan caselaw has established that a posted notice is, by itself, an appropriate way to inform a person of the proceedings against him. Another precedent notes that notice mailed to a person’s home address generally satisfies due process requirements. The Yangs argue, however, that notice by itself is not adequate, since the hearing notice did not provide the reasons for demolishing the property and the post-hearing notice would have come too late for the Yangs to prepare to defend themselves.

The Court found that all of the information contained in all of the notices, taken in the aggregate, were sufficient to meet due process requirements. Even though the Yangs did not actually receive notice, as the certified mailing was returned unclaimed, the additional efforts made by the City were reasonable attempts to contact the Yangs. The Court found the city’s attempts at contacting the Yangs were “reasonably calculated” to give the Yangs adequate notice.

Dissent

The dissent argued that the majority misconstrued the facts of the case and the contents of the notices provided by the City. The final four attempts at contacting the Yangs were not adequate because they did not provide the reasons for the potential demolition of the building, providing “less information than the average parking ticket.” The issue wasn’t whether the forms of notice were adequate, but whether the notices actually informed the owner of the issue. In the case, the dissent argues the City failed to provide the reasons for demolition in the follow-up notices and thus violated procedural due process.